The Preesall Underground Gas Storage Facility Order 2015
S.I. 2015/1561 · Made 17 July 2015 · Extends to England and Wales
Infrastructure Planning
Made 17th July 2015
Coming into force 7th August 2015
An application was made to the former Infrastructure Planning Commission in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedures) Regulations 2009f1 for an order under sections 37, 114, 115, 120, 121, 122, 123, 142 and 149A of the Planning Act 2008f2 (“the 2008 Act”).
The application was examined by a Panel appointed by the Secretary of State pursuant to Chapter 2 of Part 6 of the 2008 Actf3, and the examination was carried out in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 2010f4 (“the 2010 Rules”).
The Panel, having considered the application with the documents that accompanied it, and the representations made and not withdrawn, has, in accordance with section 74 of the 2008 Actf5 made a report and recommendation to the Secretary of State.
The Secretary of State refused the application on 9th April 2013, but, pursuant to a judgment of the High Court of Justice ([2013] EWHC 17 (Admin)) dated 17th January 2014, the Secretary of State was required to re-decide the application. The Secretary of State then invited further representations from interested parties in accordance with rule 20(2) of the 2010 Rules.
The Secretary of State, having considered the report and recommendation of the Panel and further representations received (under rule 20(2) of the 2010 Rules and otherwise), and decided the application, has determined to make an Order giving effect to the proposals comprised in the application with modifications.
The Secretary of State, in exercise of the powers conferred by sections 103, 114, 115, 120, 122, 123, 142 and 149A of the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
S.I. 2009/2264, amended by S.I. 2010/439, 602, 2012/635, 2654, 2732, 2013/522, 755.
- f2
-
2008 c. 29. The relevant provisions of the Planning Act 2008 are amended by Chapter 6 of Part 6 of, and Schedule 13 to, the Localism Act 2011 (c. 20), and by sections 22-27 of the Growth and Infrastructure Act 2013 (c. 27) (see S.I. 2013/1124 for transitional provisions).
- f3
-
Following the abolition of the Infrastructure Commission on 1st April 2012, a Panel appointed under section 61 of the 2008 Act is treated as if appointed by the Secretary of State by virtue of a direction given by the Secretary of State under section 129 of the Localism Act 2011.
- f4
-
S.I. 2010/103, amended by S.I. 2012/635.
- f5
-
Section 74 is amended by the Localism Act 2011, Schedule 13 paragraph 29(3) and Schedule 25 paragraph 1.
Contents
- Part 1: PRELIMINARY
- 1Citation and commencement
- 2Interpretation
- Part 2: WORKS PROVISIONS
- Principal powers
- 3Development consent etc. granted by the Order
- 4Maintenance of authorised development
- 5Limits of deviation
- 6Defence to proceedings in respect of statutory nuisance
- Benefit of Order
- 7Benefit of Order
- 8Transfer of benefit of Order
- Streets
- 9Street works
- 10Power to alter layout, etc., of streets
- 11Maintenance of altered streets
- 12Temporary stopping up of streets and rights of way
- 13Access to works
- 14Agreements with street authorities
- Supplemental powers
- 15Discharge of water
- 16Protective work to buildings
- 17Authority to survey and investigate the land
- Part 3: ACQUISITION AND POSSESSION OF LAND
- Powers of acquisition
- 18Compulsory acquisition of land
- 19Compulsory acquisition of rights
- 20Acquisition of subsoil only
- 21Power to override easements and other rights
- 22Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- Temporary possession of land
- 23Temporary use of land for carrying out the authorised development
- 24Temporary use of land for maintaining authorised development
- Compensation
- 25Disregard of certain interests and improvements
- 26Set-off for enhancement in value of retained land
- 27No double recovery
- Supplementary
- 28Acquisition of part of certain properties
- 29Statutory undertakers
- 30Recovery of costs of new connections
- 31Time limit for exercise of authority to acquire land compulsorily
- 32Private rights of way
- 33Rights under or over streets
- Part 4: MISCELLANEOUS AND GENERAL
- 34Application of landlord and tenant law
- 35Deemed licence for purposes of the 2009 Act
- 36Operational land for purposes of the 1990 Act
- 37Felling or lopping of trees or shrubs
- 38Protective provisions
- 39Certification of plans etc.
- 40Service of notices
- 41Arbitration
- 42Requirements
- 43Appeals relating to decisions under Requirements
- 44Crown land
- Signature
- Schedule 1: AUTHORISED DEVELOPMENT
- In the Borough of Wyre in the County of Lancashire and in the Irish Sea adjacent to the Borough of Wyre
- Schedule 2STREETS SUBJECT TO STREET WORKS
- Schedule 3STREETS SUBJECT TO ALTERATION OF LAYOUT
- Schedule 4STREETS AND RIGHTS OF WAY TO BE TEMPORARILY STOPPED UP
- Schedule 5ACCESS TO WORKS
- Schedule 6LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- Schedule 7: DEEMED LICENCE UNDER THE MARINE AND COASTAL ACCESS ACT 2009
- 1Interpretation
- 2Licence validity period
- 3Inspection of records etc.
- 4Rights of access
- 5Transfer
- 6Force majeure
- 7Licence conditions binding other parties
- 8Licensed activities
- 9Licensed location
- 10Reporting of engaged agents, contractors or sub-contractors
- 11Notification of vessels
- 12Distribution of copies
- 13Application of licence conditions
- 14Licence conditions prior to commencement of the licensed activities
- 15Licence conditions prior to commencement of the licensed activities
- 16Licence conditions prior to commencement of the licensed activities
- 17Licence conditions prior to commencement of the licensed activities
- 18Licence conditions prior to commencement of the licensed activities
- 19Licence conditions prior to commencement of the licensed activities
- 20Licence conditions prior to commencement of the licensed activities
- 21Licence conditions prior to commencement of the licensed activities
- 22Licence conditions prior to commencement of the licensed activities
- 23Licence conditions prior to commencement of the licensed activities
- 24Licence conditions prior to commencement of the licensed activities
- 25Licence conditions during construction of the licensed works
- 26Licence conditions during construction of the licensed works
- 27Licence conditions during construction of the licensed works
- 28Licence conditions during construction of the licensed works
- 29Licence conditions during construction of the licensed works
- 30Licence conditions during construction of the licensed works
- 31Licence conditions during construction of the licensed works
- 32Licence conditions during construction of the licensed works
- 33Licence conditions during construction of the licensed works
- 34Licence conditions during construction of the licensed works
- 35Licence conditions during construction of the licensed works
- 36Licence conditions during construction of the licensed works
- 37Licence conditions during construction of the licensed works
- 38Licence conditions during construction of the licensed works
- 39Licence conditions following completion of the licensed works
- 40Licence conditions following completion of the licensed works
- 41Licence conditions following completion of the licensed works
- 42Licence conditions following completion of the licensed works
- 43Changes approved by the MMO
- Schedule 8: PROTECTIVE PROVISIONS
- Part 1: FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
- 1Application
- 2Interpretation
- 3Interpretation
- 4Temporarily stopped up streets
- 5Protective works to buildings
- 6Acquisition of apparatus
- 7Removal of apparatus
- 8Facilities and rights for alternative apparatus
- 9Retained apparatus: protection
- 10Expenses
- 11Indemnity
- 12Ground subsidence monitoring scheme in respect of United Utilities’ apparatus
- 13Enactments and agreements
- 14Co-operation
- 15Access
- 16Arbitration
- Part 2: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- Part 3: FOR THE PROTECTION OF BLACKPOOL BOROUGH COUNCIL
- 1Application and interpretation
- 2Pedestrian and vehicular access
- 3Approval of plans
- 4Approval of plans
- 5Protective works
- 6Notice of works and maintenance
- 7Manner of carrying out specified and protective works
- 8Manner of carrying out specified and protective works
- 9Access for the carrying out of works in compliance with this Part
- 10Access for the carrying out of works in compliance with this Part
- 11Expenses
- 12Right to require maintenance of specified works
- 13Indemnity
- 14Indemnity
- 15Approvals and arbitration
- Schedule 9: REQUIREMENTS
- 1Interpretation
- 2Time limits
- 3Stages of authorised development
- 4Detailed design approval
- 5External materials approval
- 6Details of operational cavern layout and design
- 7European protected species
- 8Ecological management strategy scheme
- 9Landscape scheme
- 10Implementation and maintenance of landscaping
- 11Highway accesses
- 12Limits on heavy goods vehicle movements
- 13Covered heavy goods vehicles
- 14Wheel cleaning facilities
- 15Internal roads
- 16Temporary access routes
- 17Fencing and other means of enclosure
- 18Ground/surface water and pollution prevention
- 19Archaeology
- 20External lighting
- 21Construction hours
- 22Construction of and drilling operations in wellhead compound areas
- 23Code of construction practice
- 24Construction worker travel plan
- 25Disposal of filtered material
- 26Control of noise during construction and maintenance
- 27Control of noise during operational phase
- 28Control of dust emissions
- 29Protection of agricultural practice
- 30Soil stripping, handling and storage
- 31Decommissioning, restoration and aftercare scheme for submission prior to commencement of the authorised development
- 32Decommissioning of individual operational caverns during operational phase
- 33Decommissioning, restoration and aftercare scheme after permanent cessation of operations
- 34Maintenance of brine discharge pipeline, 132kV electrical circuits and NTS interconnector pipeline
- 35Ground subsidence monitoring scheme
- 36Signals
- 37River Wyre crossings
- 38Dedication agreement
- 39Requirement for written approval
- 40Amendments to approved details
- 41Changes approved by the relevant planning authority
- Explanatory note