OpenLegislation

Paragraph 12 Limits on heavy goods vehicle movementsI1

England and Wales

(1)

The maximum number of heavy goods vehicle movements to and from the Preesall site during the construction phase, operational phase and decommissioning phase shall not exceed 62 per day (31 in and 31 out).

(2)

The number of heavy goods vehicles which enter the Preesall site shall be recorded by the site operator. These records shall be available for inspection at the site office, and a copy of these records shall be submitted to the relevant planning authority every six months, or within five working days of such records being requested by the relevant planning authority.

Annotations

Commencement

I1

Sch. 9 para. 12 in force at 7.8.2015, see art. 1