Schedule 9 REQUIREMENTS

England and Wales

  1. 1Interpretation
  2. 2Time limits
  3. 3Stages of authorised development
  4. 4Detailed design approval
  5. 5External materials approval
  6. 6Details of operational cavern layout and design
  7. 7European protected species
  8. 8Ecological management strategy scheme
  9. 9Landscape scheme
  10. 10Implementation and maintenance of landscaping
  11. 11Highway accesses
  12. 12Limits on heavy goods vehicle movements
  13. 13Covered heavy goods vehicles
  14. 14Wheel cleaning facilities
  15. 15Internal roads
  16. 16Temporary access routes
  17. 17Fencing and other means of enclosure
  18. 18Ground/surface water and pollution prevention
  19. 19Archaeology
  20. 20External lighting
  21. 21Construction hours
  22. 22Construction of and drilling operations in wellhead compound areas
  23. 23Code of construction practice
  24. 24Construction worker travel plan
  25. 25Disposal of filtered material
  26. 26Control of noise during construction and maintenance
  27. 27Control of noise during operational phase
  28. 28Control of dust emissions
  29. 29Protection of agricultural practice
  30. 30Soil stripping, handling and storage
  31. 31Decommissioning, restoration and aftercare scheme for submission prior to commencement of the authorised development
  32. 32Decommissioning of individual operational caverns during operational phase
  33. 33Decommissioning, restoration and aftercare scheme after permanent cessation of operations
  34. 34Maintenance of brine discharge pipeline, 132kV electrical circuits and NTS interconnector pipeline
  35. 35Ground subsidence monitoring scheme
  36. 36Signals
  37. 37River Wyre crossings
  38. 38Dedication agreement
  39. 39Requirement for written approval
  40. 40Amendments to approved details
  41. 41Changes approved by the relevant planning authority