Paragraph 7 Manner of carrying out specified and protective worksI1

England and Wales

The construction by the promoter of the specified works, any protective works described in paragraph 5 and any alterations and additions to such specified works and protective works shall, when commenced, be carried out—

(a)

with all reasonable dispatch in accordance with the plans approved under paragraph 3 or settled under article 41 (arbitration);

(b)

under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer; and

(c)

in such manner as to cause—

(i)

as little damage as reasonably practicable to tramway property;

(ii)

as little interference as is reasonably practicable with the conduct of traffic on the tram lines of Blackpool Borough Council and the use by passengers of tramway property,

and if any such damage or interference shall be caused by the promoter carrying out the specified works or any protective works, the promoter shall, notwithstanding any approval given under paragraph 3 or settled under article 41 (arbitration), make good such damage and shall pay to Blackpool Borough Council and the operator (as appropriate) all reasonable expenses to which Blackpool Borough Council or the operator (as appropriate) may be put and compensation for any loss which Blackpool Borough Council or the operator (as appropriate) may sustain by reason of any such damage or interference.

Annotations

Commencement

I1

Sch. 8 Pt. 3 para. 7 in force at 7.8.2015, see art. 1