Paragraph 5 Cases where estimate not possibleI1I2C1
United Kingdom
If a contracting authority is unable to estimate the value of a contract in accordance with this Schedule (for example because the duration of the contract is unknown), the authority is to be treated as having estimated the value of the contract as an amount of more than the threshold amount for the type of contract.
Annotations
Modifications
- C1
Sch. 3 applied in part (24.2.2025) by S.I. 2013/1582, reg. 6(2), Sch. 2 Pt. 1 (as amended by The Procurement Act 2023 (Consequential and Other Amendments) Regulations 2025 (S.I. 2025/163), regs. 1(2), 17 (with reg. 33))
Commencement
- I1
Sch. 3 para. 5 not in force at Royal Assent, see s. 127(2)
- I2
Sch. 3 para. 5 in force at 24.2.2025 by S.I. 2024/716, Sch. (as amended by S.I. 2024/959, regs. 1(2), 2(7)(a))