Section 53 Contract details notices and publication of contractsI1I2
United Kingdom
A contracting authority that enters into a public contract must publish a contract details notice—
if the contract is a light touch contract, before the end of the period of 120 days beginning with the day on which the contract is entered into;
otherwise, before the end of the period of 30 days beginning with the day on which the contract is entered into.
A “contract details notice” means a notice setting out—
that the contracting authority has entered into a contract, and
any other information specified in regulations under section 95.
A contracting authority that enters into a public contract with an estimated value of more than £5 million must publish a copy of the contract—
if the contract is a light touch contract, before the end of the period of 180 days beginning with the day on which the contract is entered into;
otherwise, before the end of the period of 90 days beginning with the day on which the contract is entered into.
Subsection (3) does not apply in relation to a contract—
awarded by a devolved Welsh authority or a transferred Northern Ireland authority, unless it is awarded under a reserved procurement arrangement, or
awarded under a devolved Welsh procurement arrangement or a transferred Northern Ireland procurement arrangement.
A Minister of the Crown may by regulations amend this section for the purpose of changing the financial threshold.
This section does not apply—
to private utilities, or
in relation to a contract awarded under section 41 by reference to paragraph 15 of Schedule 5 (direct award: user choice contracts).
Annotations
Commencement
- I1
S. 53 not in force at Royal Assent, see s. 127(2)
- I2
S. 53 in force at 24.2.2025 by S.I. 2024/716, Sch. (as amended by S.I. 2024/959, regs. 1(2), 2(7)(a))