Section 77 Publication of modificationsI1I2
United Kingdom
Before the end of the period of 90 days beginning with the day on which a contracting authority makes a qualifying modification under section 74(1), the authority must publish a copy of—
the contract as modified, or
the modification.
A “qualifying modification” is a modification—
in respect of which the contracting authority is required to publish a contract change notice under section 75, and
which modifies, or results in, a public contract with an estimated value of more than £5 million.
Subsection (1) does not apply in relation to a modification of a contract that—
was awarded by a devolved Welsh authority, unless it was awarded as part of a procurement under a reserved procurement arrangement, or
was awarded as part of a procurement under a devolved Welsh procurement arrangement.
A Minister of the Crown may by regulations amend this section for the purpose of changing the financial threshold.
Annotations
Commencement
- I1
S. 77 not in force at Royal Assent, see s. 127(2)
- I2
S. 77 in force at 24.2.2025 by S.I. 2024/716, Sch. (as amended by S.I. 2024/959, regs. 1(2), 2(7)(a))