The Progress Power (Gas Fired Power Station) (Correction) Order 2016
S.I. 2016/736 · Made 11 July 2016
Infrastructure Planning
Made 11th July 2016
Coming into force 12th July 2016
Before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicantf4 for the correction of errors and omissions in the Progress Power (Gas Fired Power Station) Order 2015 under paragraph 1 (5)(a) of Schedule 4 to the Act.
The Secretary of State has informed Mid-Suffolk District Council and Suffolk County Council, the local planning authorities for the area in which the land to which the Progress Power (Gas Fired Power Station) Order 2015 relates is situated, that the request has been received and the statement issued, in accordance with paragraph 1(7) of Schedule 4 to the Act.
The Secretary of State, in exercise of the powers conferred by paragraph 1(4) and (8) of Schedule 4 to the Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
- f2
-
2008 c.29. Part 4 was amended by Schedule 13 to the Localism Act 2011 (c.20).
- f3
-
As provided for in Schedule 4 to the Act.
- f4
-
As defined in paragraph 4 of Schedule 4 to the Act.
Contents
1Citation and commencement
This Order may be cited as the Progress Power (Gas Fired Power Station) (Correction) Order 2016 and comes into force on 12th July 2016.
2Corrections
The Progress Power (Gas Fired Power Station) Order 2015 is to be corrected as provided for in the table in the Schedule, where—
the first column sets out where the correction is to be made;
the second column sets out how the correction is to be made; and
the third column sets out the text to be substituted, inserted or omitted.
Signature
Signed by the authority of the Secretary of State for Energy and Climate Change
Giles Scott
Head of Energy Infrastructure Planning and Coal Liabilities
Department of Energy and Climate Change
11th July 2016
| Provision | How correction is to be made | Text to be submitted, inserted or omitted |
|---|---|---|
Schedule 1, Work No. 7 | After the word “Schedule”, insert After the word “Requirements”, insert | A comma A comma and the word “and” |
| Article 6(1) | For paragraph (1), substitute |
|
| Schedule 1, Work No. 1 | After the word “gross”, insert | “rated” |
| Schedule 1, Work No. 7 | After the word “Schedule”, insert After the word “Requirements”, insert | A comma A comma and the word “and” |
| Schedule 2, Requirement 3(3), Detailed Design, in Table 2, in column 2 of the row beginning “Sealing end compound” (part of numbered Work 5) | For “12”, substitute | “12.5” |
| Schedule 2, Requirement 3(3) in Table 2, in column 2 of the row beginning “Substation: (gas insulated substation)- “(maximum compound size)” (part of numbered Work 5) | For “12”, substitute | “12.5” |
| Schedule 2, Requirement 3(3), in Table 2, in column 2 of the row beginning “Substation: (gas insulated substation)- “(indoor switchgear hall)” (part of numbered Work 5) | For “12”, substitute | “12.5” |
| Schedule 2, Requirement 5(2) | For “regulation 4”, substitute | “Requirement 4” |
Explanatory note
(This note is not part of the Order)
This Order corrects errors and omissions identified in the Progress Power (Gas Fired Power Station) Order 2015, a development consent order made under the Planning Act 2008, following a written request from the applicant under paragraph 1(5)(a) of Schedule 4 to that Act.