OpenLegislation

The Progress Power (Gas Fired Power Station) (Correction) Order 2016

S.I. 2016/736 · Made 11 July 2016

Original text. legislation.gov.uk does not revise statutory instruments, so later amendments are not shown here. Changes made to it are listed under each provision when known.

Infrastructure Planning

Made 11th July 2016

Coming into force 12th July 2016

The Progress Power (Gas Fired Power Station) Order 2015f1, which granted development consent within the meaning of the Planning Act 2008 (“the Act”)f2, contains correctable errors within the meaning of the Actf3.

Before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicantf4 for the correction of errors and omissions in the Progress Power (Gas Fired Power Station) Order 2015 under paragraph 1 (5)(a) of Schedule 4 to the Act.

The Secretary of State has informed Mid-Suffolk District Council and Suffolk County Council, the local planning authorities for the area in which the land to which the Progress Power (Gas Fired Power Station) Order 2015 relates is situated, that the request has been received and the statement issued, in accordance with paragraph 1(7) of Schedule 4 to the Act.

The Secretary of State, in exercise of the powers conferred by paragraph 1(4) and (8) of Schedule 4 to the Act, makes the following Order—

Annotations to the whole text

Footnotes

f1

S.I. 2015/1570.

f2

2008 c.29. Part 4 was amended by Schedule 13 to the Localism Act 2011 (c.20).

f3

As provided for in Schedule 4 to the Act.

f4

As defined in paragraph 4 of Schedule 4 to the Act.

Contents

  1. 1Citation and commencement
  2. 2Corrections
  3. Signature
  4. Schedule Schedule
  5. Explanatory note

1Citation and commencement

This Order may be cited as the Progress Power (Gas Fired Power Station) (Correction) Order 2016 and comes into force on 12th July 2016.

2Corrections

(1)

The Progress Power (Gas Fired Power Station) Order 2015 is to be corrected as provided for in the table in the Schedule, where—

(a)

the first column sets out where the correction is to be made;

(b)

the second column sets out how the correction is to be made; and

(c)

the third column sets out the text to be substituted, inserted or omitted.

Signature

Signed by the authority of the Secretary of State for Energy and Climate Change

Giles Scott

Head of Energy Infrastructure Planning and Coal Liabilities

Department of Energy and Climate Change

11th July 2016

ProvisionHow correction is to be madeText to be submitted, inserted or omitted

Schedule 1, Work No. 7

After the word “Schedule”, insert

After the word “Requirements”, insert

A comma

A comma and the word “and”

Article 6(1)For paragraph (1), substitute
“(1)

The provisions of this Order shall have effect solely for the benefit of the undertaker, except—

(a)

in respect of Work No. 3 and Work No. 5, the provisions of this Order shall have effect for the benefit of the undertaker and the National Grid; and

(b)

in respect of Work No. 7, the provisions of this Order shall have effect for the benefit of the undertaker and the highway authority”

Schedule 1, Work No. 1After the word “gross”, insert“rated”
Schedule 1, Work No. 7

After the word “Schedule”, insert

After the word “Requirements”, insert

A comma

A comma and the word “and”

Schedule 2, Requirement 3(3), Detailed Design, in Table 2, in column 2 of the row beginning “Sealing end compound” (part of numbered Work 5)For “12”, substitute“12.5”
Schedule 2, Requirement 3(3) in Table 2, in column 2 of the row beginning “Substation: (gas insulated substation)- “(maximum compound size)” (part of numbered Work 5)For “12”, substitute“12.5”
Schedule 2, Requirement 3(3), in Table 2, in column 2 of the row beginning “Substation: (gas insulated substation)- “(indoor switchgear hall)” (part of numbered Work 5)For “12”, substitute“12.5”
Schedule 2, Requirement 5(2)For “regulation 4”, substitute“Requirement 4”

Explanatory note

(This note is not part of the Order)

This Order corrects errors and omissions identified in the Progress Power (Gas Fired Power Station) Order 2015, a development consent order made under the Planning Act 2008, following a written request from the applicant under paragraph 1(5)(a) of Schedule 4 to that Act.