Introductory text

Original text. Later amendments are not shown.

Infrastructure Planning

Made 11th July 2016

Coming into force 12th July 2016

The Progress Power (Gas Fired Power Station) Order 2015f1, which granted development consent within the meaning of the Planning Act 2008 (“the Act”)f2, contains correctable errors within the meaning of the Actf3.

Before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicantf4 for the correction of errors and omissions in the Progress Power (Gas Fired Power Station) Order 2015 under paragraph 1 (5)(a) of Schedule 4 to the Act.

The Secretary of State has informed Mid-Suffolk District Council and Suffolk County Council, the local planning authorities for the area in which the land to which the Progress Power (Gas Fired Power Station) Order 2015 relates is situated, that the request has been received and the statement issued, in accordance with paragraph 1(7) of Schedule 4 to the Act.

The Secretary of State, in exercise of the powers conferred by paragraph 1(4) and (8) of Schedule 4 to the Act, makes the following Order—

Annotations

Footnotes

f1

S.I. 2015/1570.

f2

2008 c.29. Part 4 was amended by Schedule 13 to the Localism Act 2011 (c.20).

f3

As provided for in Schedule 4 to the Act.

f4

As defined in paragraph 4 of Schedule 4 to the Act.