Paragraph 1 Time limitsF1
England and Wales
The authorised development must commence no later than 13th August 2021.
Annotations
Textual amendments
- F1
Sch. 2 para. 1 substituted (28.7.2020) by The Progress Power (Gas Fired Power Station) (Amendment) Order 2020 (S.I. 2020/807), arts. 1, 3