Section 35 Security for completion of works partly finished or not commenced.
United Kingdom
Where the F1Treasury grant F2a local loan in aid of any work which is either partly completed or not commenced, they may, by a bond to Her Majesty or otherwise, take such security for the application of the loan to the work, and for the due completion of the work (including the raising of sufficient funds for that purpose), as they may think sufficient for securing the interest to the public.
Annotations
Textual amendments
- F1
Word in s. 35 substituted (25.2.2020) by The Public Bodies (Abolition of Public Works Loan Commissioners) Order 2020 (S.I. 2020/176), art. 1(2), Sch. 1 para. 34(2) (with art. 9)
- F2
Words in s. 35 substituted (25.2.2020) by The Public Bodies (Abolition of Public Works Loan Commissioners) Order 2020 (S.I. 2020/176), art. 1(2), Sch. 1 para. 34(3) (with art. 9)