Paragraph 55 F1
When the information process is applied to the maintenance delivery function, at least the following elements must be provided to the fleet maintenance management and maintenance development functions—
(a)
works performed in accordance with the maintenance orders;
(b)
any possible fault or defect regarding safety which is identified by the organisation;
(c)
the release to service.
Annotations
Textual amendments
- F1
Schs. 8-11 inserted (31.12.2020) by The Rail Safety (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/837), reg. 1, Sch. para. 1 (as amended in Sch. 11 paras. 14, 16, 17 by S.I. 2019/1310, reg. 1(2)(c), Sch. 1 paras. 2, 3, 4); 2020 c. 1, Sch. 5 para. 1(1)
Notes on Schedule 10
Marginal citations
- M1
Annexes IV and V of Commission Regulation (EU) No 445/2011 are substantially reproduced in Schedule 9.