Paragraph 35 Onshore decommissioningI1

England, Wales and Scotland

(1)

The undertaker must notify the relevant planning authority of the permanent cessation of commercial operation of the authorised development within 28 days following the date of permanent cessation.

(2)

Within six months of the cessation of commercial operation of the connection works an onshore decommissioning plan must be submitted to the relevant planning authority, in consultation with the relevant statutory nature conservation body, for approval unless otherwise agreed in writing by the relevant planning authority.

(3)

The approved decommissioning plan must be implemented unless otherwise agreed in writing by the relevant planning authority, in consultation with the relevant statutory nature conservation body.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 35 in force at 28.4.2025, see art. 1