OpenLegislation

Paragraph 8 Pre-construction plans and documentationI1

England, Wales and Scotland

(1)

Any archaeological reports produced in accordance with condition 7(1)(g)(iii) are to be agreed with English Heritage (and, if relevant West Sussex County Council).

(2)

Each programme, statement, plan, protocol or scheme required to be approved under condition 7 shall be submitted for approval at least four months prior to the intended start of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.

(3)

The licensed activities shall be carried out in accordance with the approved plans, protocols, statements, schemes and details approved under condition 7, unless otherwise agreed in writing by the MMO.

Annotations

Commencement

I1

Sch. 14 Pt. 2 para. 8 in force at 6.8.2014, see art. 1