OpenLegislation

Part 2A AMOUNT OF ELECTRICITY TO BE STATED IN NIROCs ISSUED FOR ELECTRICITY GENERATED USING 2013/14 CAPACITY AND 2014/15 CAPACITYF1

Generation typeAmount of electricity (in megawatt hours) to be stated in a NIROC issued for electricity generated using—
2013/14 capacity2014/15 capacity
AD1212
Advanced gasification/pyrolysis1212
Building mounted solar PV101758
Co-firing of regular bioliquid22
Dedicated biomass2323
Dedicated energy crops1212
Electricity generated from landfill gas11
Electricity generated from sewage gas22
Energy from waste with CHP11
Geopressure11
Geothermal1212
Ground mounted solar PV58F258
High-range co-firing109109
Hydroelectric107107
Low-range co-firing22
Mid-range co-firing5353
Offshore wind1212
Onshore wind109109
Standard gasification/pyrolysis1212
Station conversion11
Tidal impoundment – tidal barrage1212
Tidal impoundment – tidal lagoon1212
Tidal stream1212
Unit conversion11
Wave1212

Annotations

Textual amendments

F1

Sch. 2 Pts. 2A-2E inserted (1.5.2013) by The Renewables Obligation (Amendment) Order (Northern Ireland) 2013 (S.R. 2013/116), arts. 1(1), 33 (with art. 34)

F2

Sum in Sch. 2 Pt. 2A Table substituted (1.6.2014) by The Renewables Obligation (Amendment) Order (Northern Ireland) 2014 (S.R. 2014/146), arts. 1(1), 8 (with art. 11)