Part 2D AMOUNT OF ELECTRICITY TO BE STATED IN NIROCS ISSUED FOR ELECTRICITY GENERATED USING 2015/16 CAPACITY WHERE ARTICLE 26(5) OR (6)APPLIESF1

Generation typeAmount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the qualifying proportion of electricity generated using 2015/16 capacityAmount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the remainder of the electricity generated using 2015/16 capacity
Co-firing of regular bioliquid with CHP12
Dedicated biomass with CHP101923
High-range co-firing with CHP57109
Low-range co-firing with CHP12
Mid-range co-firing with CHP101153
Station conversion with CHP231
Unit conversion with CHP231