Regulation 4 Registration requirementsI1
England and Wales
An undertaker must register a large raised reservoir with the Agency by providing the information described in Schedule 1, paragraphs 1 to 7.
The information must be registered before the end of the period of 28 days beginning with the day of the issue of a final certificate given in accordance with section 7 of the 1975 Actf1 in relation to—
the construction of a new reservoir;
the alteration of an existing structure of a reservoir that prior to its alteration was not a large raised reservoir; or
the alteration of the area of a reservoir that prior to its alteration was not a large raised reservoir.
Annotations
Commencement
- I1
Reg. 4 in force at 30.7.2013, see reg. 1(b)
Footnotes
- f1
-
Section 7 is amended in relation to England and Wales by the Flood and Water Management Act 2010, Schedule 4, paragraphs 8 and 11 (see S.I. 2013/1590 (C.64), article 3 for relevant commencement provisions).