Section 11 Controlled reservoirs required to be registered under the 1975 Act
I1(1)
Registration under section 10 of a controlled reservoir to which subsection (2) applies must take place before the end of the period of 6 months beginning with the relevant date.
(2)
This subsection applies to controlled reservoirs which were, immediately before the relevant date, required to be registered in a large raised reservoirs register.
I2(3)
In this section and sections 12, 13 and 16—
a “large raised reservoirs register” means a register maintained under section 2(2) of the 1975 Act,
“the relevant date” means the date of commencement of section 9.
Annotations
Commencement
- I1
S. 11(1)(2) in force at 1.4.2015 by S.S.I. 2015/63, art. 2, Sch.
- I2
S. 11(3) in force at 1.1.2015 by S.S.I. 2014/348, art. 2, Sch.