Article 12 Access to worksI1

England and Wales

(1)

The undertaker may, for the purposes of the authorised project—

(a)

form, lay out and maintain means of access, or improve or maintain existing means of access, in the locations specified in F1... Schedule 6 (access to works); and

(b)

with the approval of the relevant planning authority after consultation with the highway authority in accordance with requirement 16 (highway accesses), form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised project.

(2)

If the relevant planning authority fails to notify the undertaker of its decision within 28 days of receiving an application for approval under paragraph ‎(1)(b) that relevant planning authority is deemed to have granted approval.

Annotations

Textual amendments

F1

Words in art. 12(1)(a) omitted (11.12.2024) by virtue of The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/1338), art. 1, Sch. Pt. 1 table

Commencement

I1

Art. 12 in force at 9.5.2024, see art. 1