Article 12 Access to worksI1
England and Wales As made
The undertaker may, for the purposes of the authorised project—
form, lay out and maintain means of access, or improve or maintain existing means of access, in the locations specified in F1... Schedule 6 (access to works); and
with the approval of the relevant planning authority after consultation with the highway authority in accordance with requirement 16 (highway accesses), form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised project.
If the relevant planning authority fails to notify the undertaker of its decision within 28 days of receiving an application for approval under paragraph (1)(b) that relevant planning authority is deemed to have granted approval.
Annotations
Textual amendments
- F1
Words in art. 12(1)(a) omitted (11.12.2024) by virtue of The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/1338), art. 1, Sch. Pt. 1 table
Commencement
- I1
Art. 12 in force at 9.5.2024, see art. 1