Paragraph 10 Aviation safetyI1
England and Wales
The undertaker must exhibit such lights, with such shape, colour and character as are required in writing by the Air Navigation Order 2016f1 and determined necessary for aviation safety in consultation with the Defence Infrastructure Organisation Safeguarding and as directed by the Civil Aviation Authority.
The undertaker must notify the Defence Infrastructure Organisation Safeguarding, the Civil Aviation Authority and the MMO, at least 14 days prior to the commencement of the authorised project, in writing of the following information—
the date of the commencement of construction of the authorised project;
the date any wind turbine generators are to be installed;
the maximum height of any construction equipment or vessels to be used;
the maximum height of each wind turbine generator to be constructed;
the latitude and longitude of each wind turbine generator to be constructed;
and the Defence Infrastructure Organisation Safeguarding and the Civil Aviation Authority must be notified of any changes to the information supplied under this paragraph and of the completion of the construction of the authorised project. Copies of notifications must be provided to the MMO within 5 days.