Paragraph 21 Completion of constructionI1
England and Wales As made
(1)
The undertaker must submit a close out report to the MMO, the MCA, Trinity House, UKHO and the relevant statutory nature conservation body within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include details of the latitude and longitude coordinates of the export cables, provided as Geographical Information System data referenced to WGS84 datum.
(2)
Following completion of construction, no further construction activities can be undertaken under this marine licence.