OpenLegislation

Paragraph 2 InterpretationI1

England and Wales

In this Part of this Schedule—

  • “facilities proximity area” means an obstacle-free area comprising a cylinder with a horizontal radius of one point two six nautical miles (1.26nm) extending from the centre of the existing Waveney platform located within the Licence and extending vertically from mean sea level;

  • “Licence” means United Kingdom Petroleum Production Licence P.780 Block 48/17c;

  • “Licensee” means the licensee from time to time of the Licence, who at the date hereof is Perenco;

  • “line of sight” the line of sight communications link from the existing Waveney platform located within the Licence to/from any other installation and/or to/from any onshore control room together with any associated infrastructure, equipment, software, systems, circuits, channels and licenses;

  • “Perenco” means Perenco North Sea Limited (company number SC293676) registered at C/O Dwf Llp, 2 Semple Street, Edinburgh, Scotland, EH3 8BL;

  • “pipeline” means the 8-inch (8”) diameter gas pipeline with pipeline reference number PL- 2555 connecting the Durango well to the Waveney platform located within the Licence, together with any associated umbilicals, plant and equipment serving that pipeline;

  • “pipeline proximity area” means the area five hundred (500) metres either side and directly above the pipeline; and

  • “specified works” means any works comprised within the authorised development, including temporary surface infrastructure, which are—

    1. (a)

      within the pipeline proximity area;

    2. (b)

      relate to any part of the authorised development; and

    3. (c)

      which would or may in any way adversely affect the pipeline or Licensee’s access to the pipeline,

but excluding works for the construction of wind turbine generators or offshore substation platforms.

Annotations

Commencement

I1

Sch. 14 Pt. 14 para. 2 in force at 9.5.2024, see art. 1