Paragraph 3 Works affecting the facilitiesI1

England and Wales

(1)

The undertaker must not construct, or carry out any works to install any wind turbine generators or offshore substation platforms within the pipeline proximity area or within the facilities proximity area or to adversely affect the line of sight.

(2)

No specified works are to be commenced until the undertaker and the Licensee have entered into a pipeline proximity agreement substantially in the form published by Offshore Energies UK (October 2015 edition).

Annotations

Commencement

I1

Sch. 14 Pt. 14 para. 3 in force at 9.5.2024, see art. 1