Paragraph 1 Applications made under requirementsI1
England and Wales As made
Where an application has been made to the relevant authority (“the approving authority”) for any agreement or approval required pursuant to a requirement included in this Order, the approving authority must give notice to the undertaker of their decision, including the reasons, on the application, within a period of 56 days beginning with—
the day immediately following that on which the application is received by the approving authority;
where further information is requested under F1paragraph 2, the day immediately following that on which the further information has been supplied by the undertaker; or
such longer period as may be agreed by the undertaker and the approving authority.
Annotations
Textual amendments
- F1
Words in Sch. 2 Pt. 2 para. 1(b) substituted (11.12.2024) by The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/1338), art. 1, Sch. Pt. 1 table
Commencement
- I1
Sch. 2 Pt. 2 para. 1 in force at 9.5.2024, see art. 1