Paragraph 23 Applications made under requirements
Where TfL proposes to make an application to a discharging authority for any consent, agreement or approval required by a requirement contained in Part 1 of this Schedule, no later than 28 days prior to submitting the application TfL must provide a draft of the proposed application to the discharging authority, unless otherwise agreed by the discharging authority.
At the same time as submitting a draft of a proposed application to the Council of the London Borough of Newham under sub-paragraph (1) in respect of—
any consent, agreement or approval required by paragraph 5(3) of Part 1 of this Schedule; or
any consent, agreement or approval required further to any document referred to in any such requirement,
TfL must consult the Council of the London Borough of Tower Hamlets about the draft of the proposed application and when finalising the contents of the application TfL must take into account any comments made by the Council of the London Borough of Tower Hamlets during that consultation.
An application to the discharging authority for any consent, agreement or approval required by a requirement contained in Part 1 of this Schedule must be accompanied by a statement summarising how TfL considers it has complied with the obligations applicable to the requirement set out in Part 1 of this Schedule.
Where an application has been made to the discharging authority for any consent, agreement or approval required by a requirement contained in Part 1 of this Schedule, or for any consent, agreement or approval further to any document referred to in any such requirement, the discharging authority must give notice to TfL of its decision on the application within a period of 8 weeks beginning with—
the day immediately following that on which the application is received by the discharging authority; or
where further information is requested under paragraph 24, the day immediately following that on which the further information has been supplied by TfL,
or such longer period as may be agreed in writing by TfL and the discharging authority.
Where an application has been made to the Council of the London Borough of Newham in respect of—
any consent, agreement or approval required by paragraph 5(3) of Part 1 of this Schedule; or
any consent, agreement or approval required further to any document referred to in any such requirement,
the Council of the London Borough of Newham must not give notice to TfL of its decision until the Council of the London Borough of Newham has consulted the Council of the London Borough of Tower Hamlets in respect of that application for a period of not less than 21 days, and considered any representations made by the Council of the London Borough of Tower Hamlets on the application received within that time.
In determining any application made to the discharging authority for any consent, agreement or approval required by a requirement contained in Part 1 of this Schedule, the discharging authority may—
give or refuse its consent, agreement or approval; or
give its consent, agreement or approval subject to reasonable conditions,
and where consent, agreement or approval is refused or granted subject to conditions the discharging authority must provide its reasons for that decision with the notice of the decision.