Paragraph 10 Soft landscapingI1

England, Wales and Scotland

(1)

The permitted preliminary works may start but the authorised development may not come into operation until a scheme of soft landscaping and planting has been submitted to, and approved by, the relevant planning authority.

(2)

The scheme submitted and approved under sub-paragraph (1) must include details of—

(a)

materials, and the number, species, sizes and planting positions of any planting;

(b)

measures to protect any existing shrub and tree planting that is to be retained;

(c)

an implementation plan; and

(d)

a future maintenance plan.

(3)

The scheme must be implemented within a period of 12 months beginning with the coming into operation of the authorised development and maintained as approved during the operation of the authorised development, unless otherwise agreed with the relevant planning authority.

Annotations

Commencement

I1

Sch. 2 para. 10 in force at 2.12.2021, see art. 1