The South Humber Bank Energy Centre Order 2021
S.I. 2021/1259 · Made 10 November 2021 · Extends to England, Wales and Scotland
Infrastructure Planning
Made 10th November 2021
Coming into force 2nd December 2021
The application was examined by the Examining Authority appointed by the Secretary of State pursuant to Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3.
The Secretary of State, in accordance with section 104(2) of the 2008 Act, has had regard to the documents and matters referred to in that section which the Secretary of State thinks are both important and relevant to his decision.
The Secretary of State, having considered the representations made and not withdrawn and the application with the documents that accompanied the application, has determined to make an Order giving effect to the proposals comprised in the application.
Accordingly, the Secretary of State, in exercise of the powers conferred by sections 114, 115 and 120 of the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
S.I. 2009/2264, as amended by S.I. 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522 and S.I. 2013/755.
- f2
-
2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20).
- f3
-
S.I. 2010/103, as amended by S.I. 2012/635.
Contents
- Part 1: PRELIMINARY
- 1Citation and commencement
- 2Interpretation
- 3Electronic Communications
- Part 2: PRINCIPAL POWERS
- 4Development consent etc. granted by the Order
- 5Effect of the Order on the SHBEC planning permission
- 6Maintenance of authorised development
- 7Operation of authorised development
- 8Benefit of the Order
- 9Consent to transfer benefit of the Order
- Part 3: STREETS
- 10Street works
- 11Power to alter layout, etc., of streets
- 12Construction and maintenance of new or altered means of access
- 13Temporary stopping up of streets and public rights of way
- 14Agreements with street authorities
- Part 4: SUPPLEMENTAL POWERS
- 15Discharge of water
- 16Authority to survey and investigate the land
- Part 5: OPERATIONS
- 17Felling or lopping of trees
- Part 6: MISCELLANEOUS AND GENERAL
- 18Protective provisions
- 19Statutory undertakers
- 20Apparatus and rights of statutory undertakers in stopped up streets
- 21Recovery of costs of new connections
- 22Application of landlord and tenant law
- 23Operational land for purposes of the 1990 Act
- 24Defence to proceedings in respect of statutory nuisance
- 25Certification of plans, etc.
- 26Service of notices
- 27Procedure in relation to certain approvals, etc.
- 28Requirements, appeals etc.
- 29Arbitration
- Signature
- Schedule 1AUTHORISED DEVELOPMENT
- Schedule 2: REQUIREMENTS
- 1Interpretation
- 2Commencement of the authorised development and notices
- 3Approved details and amendments to them
- 4Requirement for written approval
- 5Detailed design (position and scale)
- 6Detailed design (appearance)
- 7Retained trees
- 8Means of enclosure and hard landscaping
- 9Lighting scheme
- 10Soft landscaping
- 11Biodiversity protection
- 12Biodiversity mitigation and enhancement
- 13Surface water drainage
- 14Foul water drainage
- 15Construction environmental management plan
- 16Construction traffic management and travel planning
- 17Piling
- 18Temporary halting of development on finding unexpected contamination
- 19Investigation and remediation of contamination
- 20Implementation of remediation scheme
- 21Procedure in cases of unexpected contamination
- 22Flood risk mitigation
- 23Flood warning and evacuation plan
- 24Delivery and servicing plan
- 25Operational travel plan
- 26Visibility splays
- 27New highway access
- 28Parking
- 29Road condition survey
- 30Air safety
- 31Fuel type
- 32Fuel storage
- 33Decommissioning
- 34Amendments agreed by the relevant planning authority
- 35Combined heat and power
- 36Anticipatory steps towards compliance with any requirement
- 37Heavy goods vehicle prohibition
- 38Development consent obligation
- Schedule 3DEEMED APPROVAL OF MATTERS REFERRED TO IN REQUIREMENTS
- Schedule 4STREETS SUBJECT TO STREET WORKS
- Schedule 5STREETS SUBJECT TO PERMANENT ALTERATION OF LAYOUT
- Schedule 6: ACCESS
- 1THOSE PARTS OF THE ACCESS TO BE MAINTAINED AT THE PUBLIC EXPENSE
- 2THOSE PARTS OF THE ACCESS TO BE MAINTAINED BY THE STREET AUTHORITY
- Schedule 7STREETS TO BE TEMPORARILY STOPPED UP
- Schedule 8: PROTECTIVE PROVISIONS
- Part 1: FOR THE PROTECTION OF ANGLIAN WATER
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- Part 2: FOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY AND GAS UNDERTAKER
- 10Application
- 11Interpretation
- 12Apparatus of Undertakers in stopped up streets
- 13Acquisition of apparatus
- 14Removal of apparatus
- 15Facilities and rights for alternative apparatus
- 16Retained apparatus: protection Gas Undertakers
- 17Retained apparatus: Protection: Electricity Undertakers
- 18Expenses
- 19Indemnity
- 20Enactments and agreements
- 21Co-operation
- 22Access
- 23Arbitration
- 24Notices
- Part 3: FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
- 25Paragraph 25
- 26Paragraph 26
- 27Paragraph 27
- 28Paragraph 28
- 29Paragraph 29
- 30Paragraph 30
- 31Paragraph 31
- 32Paragraph 32
- 33Paragraph 33
- 34Paragraph 34
- 35Paragraph 35
- Part 4: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
- 36Paragraph 36
- 37Paragraph 37
- 38Paragraph 38
- 39Paragraph 39
- 40Paragraph 40
- Part 5: FOR THE PROTECTION OF NETWORK RAIL
- 41Paragraph 41
- 42Paragraph 42
- 43Paragraph 43
- 44Paragraph 44
- 45Paragraph 45
- 46Paragraph 46
- 47Paragraph 47
- 48Paragraph 48
- Explanatory note