Paragraph 24 Delivery and servicing planI1

England, Wales and Scotland

(1)

The authorised development must not come into operation until the undertaker has consulted Network Rail on an operational delivery and servicing plan for all operational HGVs entering and leaving the site, the undertaker has submitted that plan to the relevant planning authority, and the relevant planning authority has approved that plan.

(2)

The plan submitted and approved under sub-paragraph (1) must be in accordance with the operational delivery and servicing plan within annex 26 of appendix 9A of the environmental statement unless otherwise agreed by the relevant planning authority.

(3)

The plan approved under sub-paragraph (1) must be implemented as approved throughout the operation of the authorised development unless otherwise agreed by the relevant planning authority.

Annotations

Commencement

I1

Sch. 2 para. 24 in force at 2.12.2021, see art. 1