Paragraph 35 Combined heat and powerI1

England, Wales and Scotland

(1)

No part of Work No. 1 may be commissioned until a scheme for the provision of steam or hot water pass-outs has been submitted to and approved by the relevant planning authority.

(2)

The scheme submitted under sub-paragraph (1) must as a minimum comply with the conditions relating to steam and hot water pass-outs within any environmental permit granted in respect of the authorised development.

(3)

No part of Work No. 1 may be commissioned until a scheme for the provision of reserve space, suitable for the future provision of water pressurisation, heating and pumping systems for potential off-site users of process or space heating and the later connection of Work No. 1 to such systems, has been submitted to and approved by the relevant planning authority.

(4)

The scheme submitted under sub-paragraph (3) must demonstrate that the reserve space is suitable to accommodate the future installation of a pipeline connection of at least 400 millimetres in diameter.

(5)

The schemes approved under sub-paragraphs (1) and (3) must be implemented as approved prior to the coming into operation of the authorised development and maintained throughout the operation of the authorised development.

(6)

Prior to the installation of any steam or hot water pipeline in the reserve space identified within the scheme approved under sub-paragraph (3), details of the diameter and specification of the pipelines and a timetable for their installation must be submitted to and approved by the relevant planning authority and which must demonstrate that the diameter and specification of the pipelines are suitable for the connection of Work No. 1 to the identified off site users of process or space heating.

(7)

The details approved under sub-paragraph (6) must be implemented as approved and maintained, unless otherwise agreed by the relevant planning authority.

Annotations

Commencement

I1