OpenLegislation

Paragraph 20 Implementation of remediation schemeI1

England, Wales and Scotland

(1)

In the event that a remediation scheme under requirement 19(4) is required, the relevant part of the authorised development must not commence, save for the permitted preliminary works, until any scheme approved under requirement 19(4) has been implemented as approved, unless otherwise agreed by the relevant planning authority.

(2)

Following implementation under sub-paragraph (1) (in the event sub-paragraph (1) applies), the undertaker must consult the Environment Agency on a verification report that demonstrates the effectiveness of the remediation scheme which must be submitted to, and approved by, the relevant planning authority prior to the development coming into operation.

Annotations

Commencement

I1

Sch. 2 para. 20 in force at 2.12.2021, see art. 1