Paragraph 38 Development consent obligationI1

England, Wales and Scotland

(1)

Construction of Work No. 1 must not start until a development consent obligation pursuant to section 106 of the 1990 Act has been secured between the relevant planning authority, the undertaker, EP SHB Limited, and Lloyds Bank plc (or any successor in title to the charge).

(2)

The development consent obligation required by sub-paragraph (1) must reflect the obligations as secured by the section 106 agreement.

(3)

Lloyds Bank plc (or any successor in title to the charge) is not required to enter into the development consent obligation required by sub-paragraph (1) where the charge has been discharged and no longer applies to any land within the Order limits and evidence of this has been provided to the satisfaction of the relevant planning authority.

Annotations

Commencement

I1

Sch. 2 para. 38 in force at 2.12.2021, see art. 1