Paragraph 2 Phases of authorised development and date of final commissioning

Original text. Later amendments are not shown.

(1)

The authorised development must not commence until a written scheme setting out the phases of construction of the authorised development has been submitted to and approved by the local planning authority.

(2)

The scheme submitted pursuant to sub-paragraph (1) must include a timetable for the construction of the phases of the authorised development and a plan identifying the phasing areas.

(3)

The scheme submitted and approved pursuant to sub-paragraph (1) must be implemented as approved.

(4)

Notice of the date of final commissioning with respect of the first phase of Work No. 1 to complete commissioning must be given to the local planning authority within 15 working days of the date of final commissioning for that phase.