Paragraph 5 Battery safety management planI1

England, Wales and Scotland

(1)

Prior to the commencement of the BESS within Work No. 2, a BSMP must be submitted to and approved by the local planning authority in consultation with the Environment Agency and Kent Fire and Rescue Service.

(2)

The submitted BSMP must either accord with the outline BSMP or detail such changes as the undertaker considers are required.

(3)

The BSMP must be implemented as approved and maintained in accordance with the BSMP thereafter.

Annotations

Commencement

I1

Sch. 2 para. 5 in force at 13.11.2025, see art. 1

Notes on the whole SI

Textual amendments

F1

Words in Preamble substituted (6.2.2026) by The Stonestreet Green Solar (Correction) Order 2026 (S.I. 2026/131), art. 1, Sch.