Paragraph 4 Detailed design approvalI1
England, Wales and Scotland
No phase of the authorised development may be commenced until written details of—
the layout;
scale;
proposed finished ground levels;
external appearance;
hard-surfacing materials;
vehicular and pedestrian access, parking and circulation areas;
refuse or other storage units, signs and lighting;
power and communications cables and pipelines;
fencing and other means of enclosure;
security measures; and
acoustic barriers,
relating to that phase have been submitted to and approved by the local planning authority.
The written details that are submitted for approval pursuant to sub-paragraph (1) must accord with the design principles.
The authorised development must be carried out in accordance with the details approved pursuant to sub-paragraph (1).
Annotations
Commencement
- I1
Sch. 2 para. 4 in force at 13.11.2025, see art. 1
Notes on the whole SI
Textual amendments
- F1
Words in Preamble substituted (6.2.2026) by The Stonestreet Green Solar (Correction) Order 2026 (S.I. 2026/131), art. 1, Sch.