OpenLegislation

Schedule 10 DOCUMENTS AND PLANS TO BE CERTIFIEDI1

England and Wales

(1)

Document name

(2)

Document reference

(3)

Revision number

(4)

Date

F1access and rights of way plans 2.3727/11/2025
arboricultural impact assessment8.46203/03/2023
book of reference 4.31027/11/2025
Campus plan8.88121/03/2023
crash site exclusion area plan8.89003/02/2023
Deed of Obligation8.123024/03/2023
design principles8.87030/01/2023
detailed archaeology mitigation strategy8.79124/03/2023
drainage technical note8.83124/03/2023
environmental statementenvironmental statement 6.1 (excluding chapters 0, 3 and 16), 6.2 (excluding appendix 7H, 8M, 9C, 10I, 13C, 16C, 16D, 16E and 16F), 6.3 (excluding figures 3-1, 3-2, 3-17a-e, 3-20, 3-25a-d, 3-28a, 3-28b, 3-29, 3-30a, 3-30b, 3-31, 3-32, 9-1, 10-11a-f, 10-12) and 6.4018/11/2021
environmental statement 6.1 (chapter 0)130/08/2022
environmental statement 6.1 (chapter 3)211/11/2022
environmental statement 6.1 (chapter 16)111/11/2022
environmental statement 6.2 (appendix 7H)113/07/2022
environmental statement 6.2 (appendix 8M)213/01/2023
environmental statement 6.3 (figure 3-17a-e)103/03/2023
environmental statement 6.3 (figures 3-1, 3-2)224/03/2023
environmental statement 6.3 (figures 3-28a, 3-28b, 3-30a, 3-30b)114/09/2022
environmental statement 6.3 (figures 3-31, 3-32)030/08/2022
environmental statement 6.3 (figures 3-20, 3-25a-d, 3-29)130/08/2022
environmental statement 6.3 (figure 9-1)121/01/2022
environmental statement 6.3 (figures 10-11a-f, 10-12)119/10/2022
flood risk assessmentAppendix 9C contained in volume 2 of the environmental statement (document reference 6.2) – Part 1224/03/2023
Appendix 9C contained in volume 2 of the environmental statement (document reference 6.2) – Parts 2-4121/01/2022
Appendix 9C flood risk assessment addendum – Part 1124/03/2023
drainage technical note124/03/2023
FRA clarification document in light of proposed Scheme changes224/03/2023
framework construction environmental management planAppendix 16C contained in volume 2 of the environmental statement (document reference 6.2)813/09/2023
framework construction traffic management plan and travel planAppendix 13C contained in volume 2 of the environmental statement (document reference 6.2)503/03/2023
unplanned atmospheric emissions from battery energy storage systemsAppendix 16D contained in volume 2 of the environmental statement (document reference 6.2)111/11/2022
framework decommissioning environmental management planAppendix 16E contained in volume 2 of the environmental statement (document reference 6.2)413/03/2023
framework operational environmental management planAppendix 16F contained in volume 2 of the environmental statement (document reference 6.2)524/03/2023
land and Crown land plans – sheets 1–19 and 21–22 2.1630/01/2023
land and Crown land plans – sheet 202.1727/11/2025
outline battery fire safety management plan7.6424/03/2023
outline landscape and ecology management planAppendix 10I contained in volume 2 of the environmental statement (document reference 6.2)513/09/2023
outline skills, supply chain and employment plan7.7424/03/2022
potential expanded crash site exclusion area plan8.90003/02/2023
restoration overlap plan2.9018/11/2021
traffic regulation measures plans – temporary measures2.4330/01/2023
traffic regulation measures plans – temporary road closures 2.4427/11/2025
tree preservation order trees location plans8.48224/03/2023
works plans 2.2627/11/2025

Annotations

Textual amendments

F1

Words in Sch. 10 Table substituted (22.5.2026) by virtue of The Sunnica Energy Farm (Amendment) Order 2026 (S.I. 2026/667), arts. 1, 3

Commencement

I1

Sch. 10 in force at 3.8.2024, see art. 1