(1)

Notwithstanding the limits of deviation permitted pursuant to article 3(2) of this Order, no works in carrying out, maintaining or diverting the authorised development may be carried out under the trunk road at a distance within 4 metres of the lowest point of the ground.

(2)

Notwithstanding the powers granted to the undertaker pursuant to this Order, if the carrying out of any specified work would require any works to be carried out in relation to the trunk road, excluding the works authorised in relation to the A11 specified in Schedule 4 F1(streets subject to street works), and Schedule 5 Part 2 (temporary alteration of layout), the undertaker must enter into an agreement with National Highways prior to the commencement of any such work.

Annotations

Textual amendments

F1

Words in Sch. 12 para. 99(2) substituted (13.11.2024) by The Sunnica Energy Farm (Correction) Order 2024 (S.I. 2024/1154), art. 1, Sch.

Commencement

I1

Sch. 12 para. 99 in force at 3.8.2024, see art. 1