Paragraph 6 Detailed design approvalI1

England and Wales

(1)

No phase of the authorised development may commence until details of—

(a)

the layout;

(b)

scale;

(c)

proposed finished ground levels;

(d)

external appearance, including for Work No. 2, Work No. 3 and Work No. 8 how the appearance has sought to take account of the local landscape, or where this has not been possible, an explanation of why this has not been possible; but nothing in this sub-paragraph requires the undertaker to require products not currently available on the commercial market to be specifically produced for the authorised development;

(e)

hard surfacing materials;

(f)

vehicular and pedestrian access, parking and circulation areas;

(g)

refuse or other storage units, signs and lighting;

(h)

drainage, water, power and communications cables and pipelines;

(i)

how the design of that phase has taken account of either—

(i)

the arboricultural impact assessment; or

(ii)

for those trees that have not already been assessed in the arboricultural impact assessment, updated tree surveys for locations within that phase where arboricultural impacts are likely, such surveys to be carried out prior to the submission of these details and to be submitted as part of these details;

(j)

programme for landscaping works;

(k)

the pre-commencement condition survey of all public rights of way affected by haul road F1or cable route crossings has been completed in accordance with 5.2.11 of the F2framework construction traffic management plan and travel plan, and a reinstatement plan of the public rights of way surfaces and widths agreed;

(l)

how the design of that phase has taken account of predicted noise and vibration effects and mitigation proposed; and

(m)

the anti-reflective coating to be used on the solar modules in Work No. 1,

relating to that phase have been submitted and approved in writing by the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the District of West Suffolk and the District of East Cambridgeshire, both relevant planning authorities.

(2)

The details submitted must accord with the design principles, the landscape and ecology management plan for the relevant phase approved under requirement 8 and the flood risk assessment.

(3)

The authorised development must be carried out in accordance with the approved details.

(4)

The details for Work No. 2 must accord with the approved battery fire safety management plan under requirement 7 and appendix 16D of the environmental statement.

Annotations

Textual amendments

F1

Word in Sch. 2 para. 6(1)(k) substituted (13.11.2024) by The Sunnica Energy Farm (Correction) Order 2024 (S.I. 2024/1154), art. 1, Sch.

F2

Words in Sch. 2 para. 6(1)(k) substituted (13.11.2024) by The Sunnica Energy Farm (Correction) Order 2024 (S.I. 2024/1154), art. 1, Sch.

Commencement

I1

Sch. 2 para. 6 in force at 3.8.2024, see art. 1