Paragraph 19 Approval of plans and arrangementsI1
England and Wales
Before commencing the construction of any specified work the undertaker must furnish to Neath Port Authority plans of that work for its approval.
Any approval of Neath Port Authority under this paragraph—
must not be unreasonably withheld or delayed;
may be given subject to such reasonable requirements as Neath Port Authority may make for the protection of the harbour and navigation within the harbour and the approaches to the harbour, including a requirement for the undertaker to carry out protective works at its own expense;
may not vary the operation of this Order.
The undertaker must carry out any specified work and any protective works required under sub-paragraph (2) in accordance with the plans approved under sub-paragraph (1) or settled under article 50 (arbitration).
If Neath Port Authority fails to express its disapproval of any plans or arrangements within 56 days after they have been delivered to it under sub-paragraph (1), it will be deemed to have approved them.
Annotations
Commencement
- I1
Sch. 8 para. 19 in force at 30.6.2015, see art. 1