Paragraph 20 Notice of worksI1
England and Wales
The undertaker must give to Neath Port Authority not less than 56 days’ written notice of its intention to commence the construction of the specified work and, not more than 14 days after completion of such construction, must give to Neath Port Authority written notice of such completion.
Annotations
Commencement
- I1
Sch. 8 para. 20 in force at 30.6.2015, see art. 1