The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014f1 contains correctable errors, as defined in paragraph (1)3 of Schedule 4 to the Planning Act 2008f2.

Before the end of the relevant periodf3, the Secretary of State received a written request from Thames Water Utilities Limited to correct the correctable errors.

In accordance with paragraph 1(7) of Schedule 4 to the Actf4, the Secretary of State has informed the relevant local planning authoritiesf5 that the request has been received.

The Secretary of State makes this Order in exercise of the power conferred by paragraph 1(4) of Schedule 4 to the Planning Act 2008f6.

Annotations

Footnotes

f1

S.I. 2014/2384.

f2

2008 c. 29.

f3

The relevant period is the period specified in section 118(1)(b) of the Act, in accordance with paragraph 1(6)(a) of Schedule 4. Under paragraph 1(5)(a) of Schedule 4, it is a condition for the exercise of the power to make this Order that the Secretary of State receives a written request to correct the correctable errors from any person.

f4

Paragraph 1(7) of Schedule 4 was amended by the Localism Act 2011 (c. 20), Schedule 13, Part 1, paragraph 70(3).

f5

A relevant local planning authority means a local planning authority for all or any part of the area in which the land to which the decision relates is situated, under paragraph 4 of Schedule 4 to the Act.

f6

Paragraph 1(4) of Schedule 4 was amended by the Localism Act 2011, Schedule 13, Part 1, paragraph 70(3).