Paragraph 6 Construction traffic and temporary highway accessesI1

England, Wales and Scotland

(1)

No stage of the authorised development must commence until a construction traffic management plan for that stage in accordance with the outline construction traffic management plan and the mitigation measures included in the environmental statement and containing details of construction traffic and temporary highway access arrangements has been submitted to and approved in writing by the relevant planning authority in consultation with the relevant highway authority.

(2)

The construction traffic management plan for each stage must set out written details of—

(a)

construction vehicle routing;

(b)

site accesses;

(c)

the management of junctions to, and crossings of, the public highway and other public rights of way;

(d)

the scheduling and timing of movements, in particular the details of abnormal load movements;

(e)

temporary warning signs;

(f)

the marking and identification of construction vehicles;

(g)

a workforce travel plan; and

(h)

access routes along the highway network to construction compounds.

(3)

The construction traffic management plan for each stage must be implemented as approved.

Annotations

Commencement

I1

Sch. 1 Pt. 2 para. 6 in force at 25.3.2016, see art. 1