Paragraph 7 Construction hoursI1

England, Wales and Scotland

(1)

Subject to sub-paragraph (2), construction work must not take place other than between 0700 hours and 1900 hours Monday to Friday, 0700 hours and 1300 hours on Saturdays, with no activity on Sundays or bank holidays.

(2)

Work outside of the days or times in sub-paragraph (1) may take place only if—

(a)

it is associated with the hydrostatic pressure testing of the pipeline constructed as part of the authorised development;

(b)

it is associated with the horizontal directional drilling of crossings in the locations assessed in the environmental statement;

(c)

it is associated with an emergency; or

(d)

it is carried out with the prior written approval of the relevant planning authority.