Article 19 Compulsory acquisition of landI1
England, Wales and Scotland
The undertaker may acquire compulsorily so much of the Order land as is required for the authorised development or to facilitate it, or is incidental to it and may use any land so acquired for the purposes authorised by this Order or for any other purposes in connection with or ancillary to the authorised development.
This article is subject to paragraph (3), article 21, article 22 (compulsory acquisition of rights), article 25 (acquisition of subsoil etc. only), article 28 (temporary use of land for carrying out the authorised development) and article 33 (special category land).
The undertaker may only exercise the power conferred by paragraph (1) on land comprised in 1 of the 2 options for access forming part of Work no. 12 being—
the area within Work no. 12(c) as shown on the works plans and comprising plots 01/19, 01/21, 01/22, 01/30, 01/31 and 01/32 and part of plot 01/20, as shown on the lands plans; or
the area within Work no. 12(d) as shown on the works plans and comprising plots 01/27, 01/28, 01/29, 04/05, and 04/06 and part of plot 04/03 as shown on the lands plans; and
where the undertaker serves notice to treat under section 5 of the 1965 Act, or makes a declaration under section 4 of the 1981 Act over any of the land specified in either (a) or (b), it must at the same time serve on the owners of the land of the other option, a notice specifying that compulsory acquisition powers cannot be exercised over that land under this Order.
Annotations
Commencement
- I1
Art. 19 in force at 10.3.2022, see art. 1