The Thurrock Flexible Generation Plant Development Consent Order 2022
S.I. 2022/157 · Made 16 February 2022 · Extends to England, Wales and Scotland
Infrastructure Planning
Made 16th February 2022
Coming into force 10th March 2022
The application was examined by a single appointed person (appointed by the Secretary of State) pursuant to Chapter 3 of Part 6 of the 2008 Act and carried out in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3.
The single appointed person, having considered the representations made and not withdrawn and the application together with the accompanying documents, in accordance with section 83(1) of the 2008 Act, has submitted a report and recommendation to the Secretary of State.
The Secretary of State has considered the representations made and not withdrawn, and the recommendations and report of the single appointed person, and taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017f4 and, as a national policy statement has effect in relation to the proposed development, has had regard to the documents and matters referred to in section 104(2)f5 of the 2008 Act.
The Secretary of State, having decided the application, has determined to make an Order granting development consent for the development described in the application with modifications which in the opinion of the Secretary of State do not make any substantial changes to the proposals comprised in the application.
The Secretary of State is satisfied that replacement land has been or will be given in exchange for the special category land specified in the land plans and special category land plans (as defined in article 2 of this Order) as “permanent freehold acquisition” land, and the replacement land (as defined in that article) has been or will be vested in the prospective seller and subject to the same rights, trusts and incidents as attach to the special category land, and that, accordingly, section 131(4) of the 2008 Act applies.
The Secretary of State is satisfied that the special category land specified in the land plans and special category land plans (as defined in article 2 of this Order) as “acquisition of permanent new rights” land, when burdened with any new rights authorised to be compulsorily acquired under this Order, will be no less advantageous than it was before to the persons in whom it is vested, other persons, if any, entitled to rights of common or other rights, and the public, and that, accordingly, section 132(3) of the 2008 Act applies.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and schedule 5 to the 2008 Act, makes the following Order:
Annotations to the whole text
Footnotes
- f1
-
2008 c. 29. Section 37 was amended by section 137(5) of, and paragraph 5 of Schedule 13(1) to, the Localism Act 2011 (c. 20). Section 83(1) was amended by paragraph 35 of that Schedule. Section 114 was amended by paragraph 55 of that Schedule. Section 120 was amended by section 140 of, and paragraph 60 of Schedule 13(1) to, that Act.
- f2
-
S.I. 2009/2264, as amended by the Localism Act 2011 (Infrastructure Planning) (Consequential Amendments) Regulations 2012 (S.I. 2012/635) and the Infrastructure Planning (Prescribed Consultees and Interested Parties etc.) (Amendment) Regulations 2013 (S.I. 2013/522). There are other amendments to the Regulations which are not relevant to this Order.
- f3
-
S.I. 2010/103, amended by S.I. 2012/635.
- f4
- f5
-
Section 104 was amended by section 58(5) of the Marine and Coastal Access Act 2009 (c. 23) and by section 128(2) and Schedule 13, paragraphs 1 and 49(1) to (6) of the Localism Act 2011 (c. 20).
Contents
- Part 1: PRELIMINARY
- 1Citation and commencement
- 2Interpretation
- Part 2: PRINCIPAL POWERS
- 3Development consent etc. granted by the Order
- 4Limits of deviation
- 5Maintenance of authorised development
- 6Operation of generating station
- 7Benefit of Order
- 8Consent to transfer benefit of Order
- 9Defence to proceedings in respect of statutory nuisance
- 10Disapplication of legislation etc.
- Part 3: STREETS
- 11Street works
- 12Application of the 1991 Act
- 13Temporary restriction of use of streets
- 14Access to works
- 15Traffic regulation
- Part 4: SUPPLEMENTAL POWERS
- 16Discharge of water
- 17Authority to survey and investigate the land
- 18Removal of human remains
- Part 5: POWERS OF ACQUISITION
- 19Compulsory acquisition of land
- 20Statutory authority to override easements and other rights
- 21Time limit for exercise of authority to acquire land compulsorily
- 22Compulsory acquisition of rights
- 23Private rights
- 24Application of the 1981 Act
- 25Acquisition of subsoil only
- 26Modification of Part 1 of the 1965 Act
- 27Rights under or over streets
- 28Temporary use of land for carrying out the authorised development
- 29Temporary use of land for maintaining the authorised development
- 30Statutory undertakers
- 31Apparatus and rights of statutory undertakers in stopped up streets
- 32Recovery of costs of new connections
- 33Special category land
- 34Funding
- Part 6: OPERATIONS
- 35Felling or lopping of trees and removal of hedgerows
- Part 7: MISCELLANEOUS AND GENERAL
- 36Protective provisions
- 37Operational land for the purposes of the 1990 Act
- 38Certification of plans, etc.
- 39Service of notices
- 40No double recovery
- 41Application of landlord and tenant law
- 42Arbitration
- Signature
- Schedule 1AUTHORISED DEVELOPMENT
- Schedule 2: REQUIREMENTS
- Part 1: REQUIREMENTS
- 1Interpretation
- 2Time limit
- 3Notice of commencement of authorised development
- 4Detailed design
- 5Code of construction practice
- 6Construction traffic management plan
- 7Construction worker travel plan
- 8External lighting
- 9Construction hours
- 10Surface and foul water drainage
- 11Flood evacuation plan
- 12Contaminated land
- 13Archaeology
- 14Landscaping and ecological management plan
- 15Construction compound restoration
- 16Operational noise
- 17Local employment and skills strategy
- 18Operational hours
- 19Details to accord with Environmental Statement
- 20Carbon capture readiness
- 21Carbon capture readiness monitoring report
- 22Amendments to approved plans, etc.
- 23Anticipatory steps
- 24Submissions and approvals
- Part 2: APPROVAL OF MATTERS SPECIFIED IN REQUIREMENTS
- 25Applications made under requirements
- 26Further information
- 27Provision of information by Consultees
- 28Fees
- 29Appeal
- 30Documents
- Schedule 3TRAFFIC REGULATION SUSPENSION OF EXISTING TRAFFIC REGULATION ORDERS
- Schedule 4HIGHWAYS SUBJECT TO TEMPORARY CONTROL OR RESTRICTION
- Schedule 5LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN AND IN WHICH ONLY RIGHTS ETC MAY BE ACQUIRED
- Schedule 6LAND OF WHICH ONLY TEMPORARY POSSESION MAY BE TAKEN
- Schedule 7: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF RESTRICTIVE COVENANTS
- 1Compensation enactments
- 2Compensation enactments
- 3Compensation enactments
- 4Application of Part 1 of the 1965 Act
- Schedule 8: PROTECTIVE PROVISIONS
- Part 1: FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWAGE UNDERTAKERS
- 1Paragraph 1
- 2Paragraph 2
- 3Land not affected by this Part
- 4Apparatus in restricted streets
- 5Acquisition of land
- 6Removal of apparatus
- 7Facilities and rights for alternative apparatus
- 8Retained apparatus
- 9Expenses and costs
- 10Expenses and costs
- 11Cooperation
- 12Cooperation
- 13Provision for Anglian Water Services Limited
- Part 2: FOR THE PROTECTION OF ANGLIAN WATER SERVICES LIMITED
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- Part 3: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- Part 4: FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- Part 5: FOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY AND GAS UNDERTAKER
- 1Application
- 2Interpretation
- 3On Street Apparatus
- 4Apparatus of statutory undertakers in temporarily restricted streets
- 5Acquisition of land
- 6Removal of apparatus
- 7Facilities and rights for alternative apparatus
- 8Retained apparatus: protection of electricity undertaker
- 9Retained apparatus: protection of gas undertaker
- 10Expenses
- 11Enactments and agreements
- 12Co-operation
- 13Access
- 14Arbitration
- 15Notices
- Part 6: FOR THE PROTECTION OF NETWORK RAIL
- 1Part to have effect unless otherwise agreed
- 2Interpretation
- 3Interpretation
- 4Interpretation
- 5Interpretation
- 6Interpretation
- 7Interpretation
- 8Interpretation
- 9Interpretation
- 10Interpretation
- 11Interpretation
- 12Interpretation
- 13Interpretation
- 14Interpretation
- 15Interpretation
- 16Interpretation
- 17Interpretation
- 18Interpretation
- 19Interpretation
- 20Interpretation
- 21Interpretation
- Part 7: FOR THE PROTECTION OF PORT OF TILBURY LONDON LIMITED
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- Part 8: FOR THE PROTECTION OF HIGHWAYS ENGLAND COMPANY LIMITED
- 1Application
- 2Interpretation
- 3Approvals
- 4Construction of the authorised development
- 5Payments
- 6Interaction with the Lower Thames Crossing
- 7Expert determination
- Part 9: FOR THE PROTECTION OF RWE GENERATION (UK) Plc
- 1Paragraph 1
- 2Paragraph 2
- 3Exercise of Powers
- 4Existing apparatus
- 5Road, proposed road and RWE Undertaking
- 6General
- 7General
- 8Notices
- Part 10: FOR THE PROTECTION OF THURROCK BOROUGH COUNCIL
- 1Paragraph 1
- 2Paragraph 2
- 3Road condition surveys
- 4Road condition surveys
- 5Road condition surveys
- 6HGV route remediation
- 7HGV route remediation
- 8HGV route remediation
- 9Specified works
- 10Specified works
- 11Specified works
- 12Level crossing warning illuminated signage
- 13Payment of invoices
- 14Disputes
- 15Indemnity
- Explanatory note