Paragraph 12 Level crossing warning illuminated signageI1

England, Wales and Scotland

(1)

The illuminated signage is to be located in the vicinity of the new junction to be formed from the new access road (Work no. 6 authorised by this Order) on to Station Road.

(2)

The Council will prepare a design for the illuminated signage in consultation with Network Rail within 8 weeks of being requested to do so by the undertaker, or 8 weeks from the date of receipt of the notice of commencement of the authorised development, whichever is the earlier.

(3)

The Council must obtain any Consents required to install the illuminated signage.

(4)

The Council is responsible for approving, procuring, carrying out, supervising and, inspecting any works associated with installing the illuminated signage.

(5)

The Council must carry out any RSAs which are required in relation to the design and installation of the illuminated signage.

(6)

The Council must use best endeavours to carry out the works to install the illuminated signage no later than 6 months from the date of commencement of the authorised development.

(7)

The Council will invoice the undertaker for its reasonably incurred costs under this paragraph as soon as reasonably practicable following installation of the illuminated signage.

Annotations

Commencement

I1

Sch. 8 Pt. 10 para. 12 in force at 10.3.2022, see art. 1