Paragraph 10 Surface and foul water drainageI1
England, Wales and Scotland
No part of the authorised development can commence until written details for that part have been submitted to and approved by the relevant planning authority.
The details submitted under sub-paragraph (1) must include—
the means of pollution control;
connection points to existing drainage network with consideration to directing drainage away from the West Tilbury Main catchment; and
ground raising and effects on the routing of flood waters.
The details submitted under sub-paragraph (1) must be in accordance with the conceptual drainage strategy certified under article 38.
The surface and foul water drainage system for the relevant part of the authorised development must be constructed and maintained in accordance with the approved details unless otherwise agreed in writing by the relevant planning authority.