Paragraph 5 Road condition surveysI1
England, Wales and Scotland
(1)
The Council will invoice the undertaker for the reasonable anticipated costs of all of the planned road conditions surveys set out in the scope following the finalisation of the scope.
(2)
Where the costs incurred by the Council exceed the sum invoiced under sub-paragraph (1) because the development did not complete in accordance with the programme notified to the Council under paragraph 4(1)(b), the Council may, following the carrying out of the final survey under sub-paragraph 4(3), invoice the undertaker for the costs incurred in excess of the sum invoiced under sub-paragraph (1).
Annotations
Commencement
- I1
Sch. 8 Pt. 10 para. 5 in force at 10.3.2022, see art. 1