Paragraph 5 Code of construction practiceI1
England, Wales and Scotland
No part of the authorised development can commence until a code of construction practice for that part has been submitted to and approved by the relevant planning authority.
The code of construction practice must be substantially in accordance with the outline code of construction practice and—
include relevant measures relied on in the environmental statement; and
include management plans, working methods and mitigation measures including—
details of lighting during construction;
pollution incident control plan;
soil management strategy; and
dust management and monitoring plan.
Construction of the authorised development must be carried out in accordance with the approved code of construction practice.