Paragraph 4 Detailed designI1
England, Wales and Scotland
No part of the authorised development can commence until written details of the following for that part have been submitted to and approved by the relevant planning authority specifying—
the siting, design, external appearance, dimensions and floor levels of all permanent buildings and structures;
the colour, materials and surface finishes of all permanent buildings and structures; and
details of the provision made for cycle parking facilities for staff.
The details to be submitted for approval under sub-paragraph 9(1) must—
be in accordance with the design principles statement;
include flood resistance and resilience measures for a flood level of up to 2.84m above Ordnance Survey datum for critical equipment; and
include appropriately scaled plans and sectional drawings.
No works creating or affecting culverts in ordinary watercourses or the balancing pond east of Fort Road may be commenced unless the detail of such works has been approved by the relevant planning authority in consultation with Thurrock Council in its capacity as the lead local flood authority.
In so far as the details submitted under paragraph (1) relate to Work no. 4, the relevant planning authority must consult Highways England on those details prior to issuing any approval under that paragraph.
The authorised development must be designed in accordance with the parameters specified in Table 1 below and the works plans and constructed in accordance with approved plans and any other approvals given by the relevant planning authority pursuant to this requirement.
Table 1
| Parameter | Work no.s | Maximum value(s) and unit |
|---|---|---|
| Gas engine exhaust stack height | 1A(c) | 43m AOD |
| Gas engine building(s) or equipment dimensions (in total) | 1A(a, b, d, e, f) | Width: 135m Length: 265m Height: 20m |
| Battery building(s) or containers dimensions (in total) | 1B | Width: 106m Length: 106m Height: 10m |
| Customer substation equipment height | 1C(l) | 15m |
| Height of all equipment and structures within Work 1 not otherwise specified | 1 | 10m |
| National grid gas connection compound dimensions | 5A | Width: 50m Length: 50m Height: 5m |
| Gas pipeline(s) maximum excavation depth | 4 | 4m for trenched or 5m below base of feature crossed for trenchless construction |
| Underground cable(s) maximum depth | 3A | 4 m for trenched or 5 m below base of feature crossed for trenchless construction |
| Road construction working corridor width | 6 | 20 m |
| Gas pipeline construction working corridor width | 4 | 23 m |
| CCR minimum area | n/a | 32,100 m2 |
| Footbridge to replacement common land | 13 | Must be a clear span structure |
The buildings and structures identified in Table 1 must only be constructed within the area for the work of which they form part as shown in the works plans.
The details submitted for Work no.12 under sub-paragraph (1) may only include details for either Work no.12(c) or Work no.12(d), and must specify which of Work no. 12(c) or Work no.12(d) is to be developed.
In so far as the details submitted under paragraph (1) relate to Work nos. 4, 6 and 7, the relevant planning authority must consult Network Rail on those details where the relevant works may impact Network Rail property and ensure:
in respect of Work no. 4, any part of that work is situated over 200 metres from Network Rail property;
in respect of Work no. 6, any part of that work is situated over 15 metres from Network Rail property; and
in respect of Work no. 7, any part of that work is situated over 15 metres from Network Rail property.
Annotations
Commencement
- I1
Sch. 2 para. 4 in force at 10.3.2022, see art. 1